PSC Resolves Complaint Approves Remediation Plan for Windstream


FOR IMMEDIATE RELEASE

            PSC RESOLVES COMPLAINT APPROVES
            REMEDIATION PLAN FOR WINDSTREAM


Lincoln, October 16, 2024- The Nebraska Public Service 
Commission (PSC) has issued an Order (911-078/DC-
104/C-5596) approving a stipulated agreement with 
Windstream and dismissing the department complaint 
against the telecommunication carrier concerning three 
separate 911outages/disruptions.

“Through this agreement Windstream has committed to 
improving public safety communications by investing 
more than one million dollars into its network reliability 
and diversity, ”said Commission Chair Dan Watermeier. 
“ The agreement provides for civil penalties if 
Windstream does not complete the agreed upon 
enhancements and improvements by the end of 2025.”

The agreement includes a 911 Remediation Plan, in which
Windstream has agreed, among other improvements to:

  • Enhance its back up systems to address power outages.
     
  • Provide an additional layer of reliability and protection
    against outages by adding a new network path. This
    additional path creates three separate network paths for
    traffic into and out of Nebraska. This third path has the
    capacity to carry all of Windstream’s traffic in Nebraska
    should the other two paths go down and repairs need to
    be made.
     
  • Engage a third-party auditor to complete a system
    reliability and engineering review of its Nebraska network.

The stipulated agreement follows an investigation involving 
three separate Windstream service disruptions which 
occurred on September 2 & 3, November 28, 2023, and 
January 13, 2024. As part of its investigation the Commission 
conducted data  requests, held a public hearing, and sought 
analysis from outside experts on network infrastructure 
specifically in the area of 911 network requirements. As a 
result of the investigation a complaint was filed by the State 
911 department. The department complaint resulted in the 
stipulated agreement and the remediation plan approved 
by the Commission.

Commissioner Watermeier said, “The Commission and the 
public demand accountability from our telecommunications 
carriers. While we appreciate Windstream’s willingness to 
work with us, we will continue to monitor the company’s 
progress to confirm that it is complying with the agreement.”

With the Order dismissing the complaint and approving the 
stipulated agreement, a hearing will not be held. A copy of 
the Order as well as the Remediation Plan can be found on 
the PSC website at <https://psc.nebraska.gov/state-911/
windstream-911-outage-investigation >. ###

Contact:
Deb Collins- Communications & Media Mgr.
(402) 471-0226
deb.collins@nebraska.gov

PSC Front